Appendix 1
- University of Washington Press
- Chapter
- Additional Information
273 HANFORD FACILITY STARTING DATE COMPLETION DATE 100-b processing area (b reactor) June 7, 1943 sept. 15, 1944 100-d processing area (d reactor) nov. 1, 1943 dec. 4, 1944 100-f processing area (f reactor) dec. 21, 1943 feb. 10, 1945 200-e processing area (canyon) aug. 2, 1943 feb. 10, 1945 200-W processing area (canyon) June 22, 1943 dec. 16, 1944 200-n processing area (canyon) nov. 17, 1943 nov. 3, 1944 300 area June 10, 1943 Jan. 6, 1945 700 administrative area (richland) sept. 14, 1943 mar. 31, 1945 1100 richland village (residential) apr. 9, 1943 mar. 31, 1945 E.I. du Pont de Nemours & Co., Inc., “Completion Report, Manhattan District, Hanford Engineer Works TNX Plant,” Apr. 30, 1945, MEDPR, box 46. Appendix 1 starting and completion dates of manhattan Project facilities at hanford, 1943–45 ...